CCS and Power Systems

Advanced Energy Systems - Advanced Combustion Systems


Recovery Act: Oxy-Combustion Technology Development for Industrial-Scale Boiler Applications


Performer: Alstom Power Inc

Project No: NT0005290


Contacts, Duration, and, Cost

Contacts

Shailesh D. Vora
Technology Manager
Existing Plants, Emissions & Capture
National Energy Technology Laboratory
626 Cochrans Mill Road
P.O. Box 10940
Pittsburgh, PA 15236-0940
412-386-7515
shailesh.vora@netl.doe.gov

Tim Fout
Project Manager
National Energy Technology Laboratory
3610 Collins Ferry Road
P.O. Box 880
Morgantown, WV 26507-0880
304-285-1341
timothy.fout@netl.doe.gov

Armand A. Levasseur
Principal Investigator
Alstom Power, Inc.
U.S. Power Plant Laboratories
2000 Day Hill Road
Windsor, CT 06095-0500
860-285-4777
levasseur@power.alstom.com


Duration
Award Date: 10/01/2008
Project Date: 04/30/2014


Cost
DOE Share: $15,000,000.00
Performer Share: $5,512,786.00
Total Award Value: $20,512,786.00


Project Details